O'Connor: Rebuilding Forbes Avenue bridge could take 2 years, more than $10M

Mary Ann Thomas
4697806_web1_ptr-BridgeReplacement-013122
Tribune-Review
The aftermath Sunday of the collapsed Forbes Avenue bridge over Fern Hollow in Frick Park.

Declarations of emergency from Pittsburgh Mayor Ed Gainey and Gov. Tom Wolf could help fast-track federal and state money to help pay for the cleanup and construction of the Forbes Avenue bridge over Fern Hollow in Frick Park.

How quickly the process will move along is uncertain, but constructing a new bridge could take about two years and will cost more than $10 million, estimated City Councilman Corey O’Connor, who represents the communities impacted by the bridge collapse.

“Looking at funding, there’s the infrastructure bill at the federal level, but I’m not sure how that money will trickle down to the municipalities,” O’Connor said. “Those conversations are already happening.”

The nearly half-century-old bridge collapsed Friday, injuring 10 people. The National Transportation Safety Board was on-site Saturday investigating the collapse.

Gainey’s office said in a news release Sunday the mayor would be signing a Declaration of Disaster Emergency.

“This declaration will increase the availability of federal funds, facilitate closer coordination between PennDOT and Department of Mobility and Infrastructure, and expedite the process of cleanup and reconstruction of the Fern Hollow Bridge,” the release said.

The governor’s proclamation of disaster emergency, signed Friday, “hopefully will open up expediting funds for this project,” O’Connor said.

U.S. Sen. Bob Casey on Sunday pledged to help find federal funds to reconstruct the bridge.

“I am committed to working with Gov. Wolf, PennDOT and local officials to ensure that we secure funding to repair the Fern Hollow Bridge using emergency funds or funds from the infrastructure law,” he said.


Related

Residents near collapsed Forbes Avenue bridge adjusting to traffic, longer commutes
Photos: Bridge collapse in Pittsburgh’s Frick Park
Pittsburgh couple who survived bridge collapse thought they were going to die, twice
Complete coverage of the bridge collapse


The bridge collapse underscores the need for massive investments in bridge repairs through the Infrastructure Investment and Jobs Act, Casey added.

O’Connor said he expects the Forbes Avenue bridge project to be similar in process and duration to the Greenfield Bridge project.

That span fell into disrepair and was imploded in late 2015. It was rebuilt and reopened in October 2017. The project cost about $15.5 million.